Q1:
A task has an early start of day 4. late start of day 14. early finish of day 10. and a late finish of day 20. What is the task's float?
○
A
4○
B
10○
C
20○
D
9
AACE International
CCP
Q2:
Which statement best describes the constructability review for a project?
○
A
Is concerned primarily with resource scheduling and organizational planning○
B
The review by a multi-discipline team to Improve the methods of delivering the intended scope○
C
A method to reduce costs by considering alternate designs○
D
The systematic application of recognized techniques which identify the functions of the product or service
AACE International
CCP
Q3:
AACE International defines_____________as the primary activity that separates Value Methodology (VM) from other "improvement" practices and has the objective
to develop the most beneficial areas for continuing study.
○
A
Not present worth method○
B
Benefit/Cost ratio (B/C) method○
C
Function Analysis Phase○
D
Life cycle costs method (LCC)
AACE International
CCP
Q4:
How can the quality of a cost/capacity factor estimate be improved?
○
A
Validate the capacity factor from similar, recently completed projects○
B
Validate law productivity from recently completed projects○
C
Verify the labor rates used in the estimate○
D
Verify the equipment costs used in the estimate
AACE International
CCP
Q5:
Which of the following is NOT a part of the five (5) phases of value engineering?
○
A
Cost reduction○
B
Functional analysis○
C
Creative○
D
Information gathering