A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.
Which feature of the Gantt chart will help them understand this?
The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
A project manager has assigned a task to a team. One of the members of the team wants to volunteer to complete the task.
Where would the volunteer navigate to do this?
Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?