Q1:
Rbi as an integrated management tool that complements.
○
A
Pha and rcm
API
API-580
Q2:
A Rbi analysis shares many of the techniques and data requirements with a____________.
○
A
Qra○
B
Pha○
C
Hazop○
D
Event tree
API
API-580
Q3:
Some failures have potentially serious consequences, but if the probability of the incident is low, then
○
A
The risk may not warrant immediate action○
B
The risk may warrant immediate action○
C
The risk may warrant appropriate mitigation action
API
API-580
Q4:
Act of mitigating a known risk to a lower level of risk.
○
A
Risk reduction○
B
Risk management○
C
Risk mitigation
API
API-580
Q5:
Rbi is focused on a systematic determination of
○
A
Relative risks○
B
Absolute risks○
C
Comparable risks○
D
Total risks