A facility, function, department, or resource whose capacity is equal to or less than the demand placed upon it is known as:
○
A
timeframe○
B
bottleneck○
C
elapsed operation○
D
none of the above
APICS
CPIM
Q2:
The files contained in the database are of two types which are:
○
A
planning and control○
B
planning and procedural○
C
fixed and variable○
D
absolute and relative
APICS
CPIM
Q3:
The capacity required depends on the particular mix of products being built and is difficult to predict is a characteristic of:
○
A
Intermittent manufacturing○
B
process improvement○
C
Streamline manufacturing○
D
Periodic manufacturing
APICS
CPIM
Q4:
What is characterized by many variations in product design, process requirements and order quantities?
○
A
Intermittent manufacturing○
B
process improvement○
C
Streamline manufacturing○
D
Periodic manufacturing
APICS
CPIM
Q5:
The formula to calculate the rated capacity is:
○
A
Rated capacity = actual time * utilization * efficiency○
B
Rated capacity = available time * utilization * efficiency○
C
Rated capacity = available time * performance * efficiency○
D
Rated capacity = expected time * number of workers * efficiency