Q1:
An integrator has to upgrade a camera system in an existing board room. What is the MOST IMPORTANT information to gather on the site visit?
○
A
cable length○
B
ambient lighting placement○
C
resolution of camera system○
D
distance from the lens to first participant
Avixa
CTS
Q2:
When is the optimal time to conduct training of end users in a new AV installation?
○
A
after all participants have reviewed equipment manuals○
B
when all users of the facility can be trained at the same time○
C
at the time of system handover with accompanying user guides○
D
during installation so that the system can be configured and modified in line with the user's knowledge
Avixa
CTS
Q3:
"Shock Loads" for equipment mounts refer to
○
A
suspended equipment not electrically isolated from Its mounting structure.○
B
sudden additional loads from earthquakes or personnel hanging from the mounts.○
C
calculated counterweight required to balance an offset load on a cantilever mount.○
D
calculated isolation required to eliminate vibration otherwise transferred to the building structure.
Avixa
CTS
Q4:
According to AVIXA Standards, what is the MINIMUM load rating for truss that will hold a 5000 lbs (2268 kg) LED wall?
○
A
15000 lbs (6804 kg)○
B
25000 lbs (11340 kg)○
C
30000 lbs (13608 kg)○
D
50000 lbs (22678 kg)
Avixa
CTS
Q5:
In a request for proposal (RFP) document, what would be the BEST place to find the overall expectations and contractual requirements for the project?
○
A
scope of work○
B
block diagram○
C
bill of materials○
D
system drawings