Available Number of Questions: Maximum of
64 Questions
Exam Name: Advanced Test Manager
Exam Duration: 90 Minutes
Related Certification(s):
ISTQB Test Manager Certification
ISTQB ATM Exam Topics - You’ll Be Tested in Actual Exam
The ISTQB ATM exam covers a range of essential topics related to software testing and quality assurance. One of the key areas is test planning and estimation, which involves understanding the scope of testing, defining test objectives, and creating a comprehensive test strategy. This includes estimating the effort and resources required, as well as determining the appropriate test levels and types. Another crucial topic is test design techniques, where you learn various methods to design effective test cases. This encompasses techniques like equivalence partitioning, boundary value analysis, and decision table testing, ensuring thorough coverage of the software's functionality. Test execution is also a significant aspect, focusing on the practical implementation of test cases, executing them in a controlled environment, and accurately recording the results. Additionally, the exam delves into test automation, exploring the benefits and challenges of automating test processes. It covers selecting appropriate automation tools, developing automated test scripts, and maintaining and updating them effectively. Furthermore, test management is an integral part, emphasizing the organization and coordination of testing activities. This includes test planning, scheduling, and tracking, as well as managing test environments and resources. The exam also addresses test measurement and reporting, teaching you how to collect and analyze test metrics to assess the quality and progress of the testing process. Finally, test improvement is a vital topic, encouraging continuous improvement in testing practices. It involves identifying areas for enhancement, implementing changes, and learning from past experiences to optimize future testing efforts.
ISTQB ATM Exam Short Quiz
Attempt this ISTQB ATM exam quiz to self-assess your preparation for the actual ISTQB Advanced Test Manager exam. CertBoosters also provides premium ISTQB ATM exam questions to pass the ISTQB Advanced Test Manager exam in the shortest possible time. Be sure to try our free practice exam software for the ISTQB ATM exam.
1of 0 questions |
ISTQB ATM Exam Quiz
✓ 0 answered
🔖 0 bookmarked
ISTQBATM
Q1:
After the presentation, you are asked to explain the chart. Assume you have applied a full risk-based testing strategy.
Which of the following answers would you expect to best describe the pie chart?
K4 3 credits
○
AAll the risk items have been covered with tests. No more risk items remain to test
○
BAccording to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application
○
COnly the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas
○
D97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test
ISTQBATM
Q2:
Which of the following factors could negatively influence a review?
K2 1 credit
○
AInclude people with the adequate level of knowledge, both technical and procedural
○
BInclude people who are detail-oriented and scrupulous at finding issues
○
CInclude as many people as possible in order to have more viewpoints about possible problems on the item under review
○
DInclude people able to contribute to a clear, thoughtful, constructive and objective discussion
ISTQBATM
Q3:
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.
You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.
On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).
Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?
K4 3 credits
○
AManagement support
○
BParticipant support
○
CDefinition and use of metrics to measure the ROI (Return On Investment)
○
DTraining in the review process
ISTQBATM
Q4:
Consider the following list of statements about audits and management reviews:
Audits are usually more effective than management reviews at finding defects
Audits and management reviews have the same main goals, the only difference is related to the roles and level of formality
A typical outcome of an audit includes observations and recommendations, corrective actions and a pass/fail assessment
An audit is not the appropriate mechanism to use at the code review in order to detect defects prior to dynamic testing
Which of the following statements is true?
K2 1 credit
○
AI. and III. are true; II. and IV. are false;
○
BII. and III are true; I. and IV. are false;
○
CIII. and IV. are true; I and II are false;
○
DI, III and IV are true; II. is false;
ISTQBATM
Q5:
The main objectives the senior management team wants to achieve are:
- to reduce the costs associated with dynamic testing
- to use reviews to ensure that the project is on course for success and following the plan
- to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles
- to determine the effectiveness of reviews in terms of phase containment
- to improve phase containment effectiveness
Which of the following answers would you expect to describe the best way to achieve these objectives?
K4 3 credits
○
AYou should plan for lightweight exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects
○
BYou should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects
○
CYou should plan for formal exit-phase reviews at the end of each development phase and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the people responsible for those bugs
○
DYou should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the phase in which they have been introduced