Q1:
Which of the following is not true about programme control?
○
A
Programme control provides supporting activities to refine and improve delivery○
B
Programme control minimizes impact of ambiguity○
C
Programme control defines reporting mechanism○
D
Programme control justifies continuance of programme
PeopleCert
MSP Practitioner
Q2:
Which of following is NOT part of delivering the capability?
○
A
Start Projects○
B
Governance: Manage and control delivery○
C
Align projects with benefits realization○
D
Gateway reviews
PeopleCert
MSP Practitioner
Q3:
Which of the following is NOT normally a characteristic of the Vision Statement?
○
A
It must describe a desirable future○
B
It is short○
C
Key benefits are implicit○
D
It must be time dependent
PeopleCert
MSP Practitioner
Q4:
Which of following is not a principal control for managing the tranches?
○
A
Business Case○
B
Benefit Review○
C
Business Case○
D
Dependency management
PeopleCert
MSP Practitioner
Q5:
Which is not a valid response for a threat?
○
A
Avoid○
B
Enhance○
C
Accept○
D
Reduce