Q1:
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
○
A
Resource availability○
B
Infrastructure○
C
Academic research○
D
Corporate knowledge base
PMI
CAPM
Q2:
What estimating technique is used when there is limited information?
○
A
Analogous estimating○
B
Parametric estimating○
C
Bottom-up estimating○
D
Three-point estimating
PMI
CAPM
Q3:
During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?
○
A
Initiating○
B
Planning○
C
Executing○
D
Monitoring and Controlling
PMI
CAPM
Q4:
What statement describes the function or responsibility of a project manager?
○
A
Works with the sponsor to address internal political and strategic issues that may impact the team○
B
Seeks ways to develop relationships that assist the team in achieving organizational goals and objectives○
C
Ensures that the project's business operations are efficient○
D
Provides management oversight for a project's functional or business units
PMI
CAPM
Q5:
In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?
○
A
Matrix - strong○
B
Matrix - balanced○
C
Virtual○
D
Functional