Which statement about the 'initiating a project' process is CORRECT?
○
A
The initiation stage plan should form part of the project plan○
B
The impact of frequent releases on quality management should be assessed○
C
The process should take more time than usual for disruptive projects○
D
The project solution should be documented in detail in the project product description
PRINCE2
PRINCE2-Agile-Foundation
Q2:
Which is a purpose of the plans theme?
○
A
To identify any deviations from the project's objectives○
B
To control any approved changes to the baseline○
C
To monitor actual achievements against those planned○
D
To communicate the approach for delivering products
PRINCE2
PRINCE2-Agile-Foundation
Q3:
When creating the project product description, how should the purpose of the project product be defined?
○
A
As an opportunity○
B
As a vision○
C
As an outcome○
D
As a goal
PRINCE2
PRINCE2-Agile-Foundation
Q4:
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.
○
A
1 and 2○
B
2 and 3○
C
3 and 4○
D
1 and 4
PRINCE2
PRINCE2-Agile-Foundation
Q5:
What does velocity typically measure?
○
A
Work packages completed by the team○
B
The rate of progress the team is making○
C
The number of timeboxes completed○
D
The speed that a minimum viable product is created