Q1:
The 'capability to provide health and safety training' has been delivered. During the 'closing a project' process, the marketing department sent an e-mail to all key customers reminding them of the deadline to comply with the new government legislation, with an aim to build relationships with their customers.
Which theme is being applied?
○
A
Risk.○
B
Organization.○
C
Plans.○
D
Change.
PRINCE2
PRINCE2 Practitioner
Q2:
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
○
A
Scope, People & Resources, Benefit○
B
Scope, Risk, Product○
C
Risk, Benefit, Product○
D
Scope, Risk, Benefit
PRINCE2
PRINCE2 Practitioner
Q3:
Which principle is supported by the activity Evaluate the Project?
○
A
Continued Business Justification○
B
Defined roles and responsibilities○
C
Learn from experience○
D
Manage by stages
PRINCE2
PRINCE2 Practitioner
Q4:
Which of the following activities is NOT an action of preparing for planned closure?
○
A
Update the project plan with actual○
B
Update the Project Management Team○
C
Request a product status account○
D
Confirm project has delivered what is defined in Project Product Description
PRINCE2
PRINCE2 Practitioner
Q5:
Which of the following statements is FALSE regarding the Continued Business Justification?
○
A
The justification for the project must remain the same throughout the project.○
B
The justification for the project should remain vabd.○
C
The justification for the project may change.○
D
If the project is no longer justified it should be stopped.