SAP
C_TS422_2504
Q1:
What does the material type influence?
Note: There are 2 correct answers to this question.
☐
A
Which document types class categories are allowed☐
B
Which plantspecific plantindependent statuses are allowed☐
C
Which material master screens appear in which sequence☐
D
Whether the material is produced inhouse procured externally or both
SAP
C_TS422_2504
Q2:
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
☐
A
Opening period☐
B
Total replenishment lead time☐
C
Float after production☐
D
Setup time
SAP
C_TS422_2504
Q3:
Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.
☐
A
In the production version☐
B
In the work centers☐
C
In the bill of material (BOM)☐
D
In the MRP controller☐
E
In the routing
SAP
C_TS422_2504
Q4:
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.
☐
A
Quantity☐
B
Status☐
C
Installation point☐
D
Scrap percentage
SAP
C_TS422_2504
Q5:
Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
☐
A
Assign planned orders manually in the planning table.☐
B
Run MRP with quota arrangement.☐
C
Run MRP with automatic selection of production version.☐
D
Run PP/DS heuristics for repetitive manufacturing.