An architect is tasked with helping a customer develop a design that meets the following requirements:
Must have no single point of failure
Must include thorough standard operating procedure documentation
Must use VMXNET3 virtual network interface card
Must have 99.9% uptime Service Level Agreement
Must use the latest version of VMware vSphere
Which two are considered constraints? (Choose two.)
An architect has been tasked with designing a greenfield hosting platform.
As part of a workshop, it is identified that the new solution must support the following:
Provide a centralized way to enforce virtual network security policy
Provide network security for both virtual machines and containerized applications
Deny network access between all workloads by default
Linked services should be connected to the same virtual port groups by default
Support for the security teams network monitoring solution
Which elements should the architect include in the design to meet the identified requirements?
An architect is documenting the design for a new multi-site vSphere solution. The customer has informed the architect that the workloads hosted on the solution are managed by application teams who must perform a number of steps to return the application to service following a failover of the workloads to the secondary site. These steps are defined as the Work Recovery Time (WRT). The customer has provided the architect with the following information about the workloads, including the recovery time objective (RTO) and recovery point objective (RPO):
Critical workloads have a WRT of 12hours
Production workloads have a WRT of 24hours
Development workloads have a WRT of 24hours
All workloads have an RPO of 4hours
Critical workloads have an RTO of 1hour
Production workloads have an RTO of 12hours
Development workloads have an RTO of 24hours
The customer has also confirmed that production and development workloads are managed by the same team and the disaster recovery solution will not begin the recovery of the development workloads until all critical and production workloads have been recovered at the secondary site.
Which three statements would the architect document as the maximum tolerable downtime (MTD) for workloads within the design? (Choose three.)
An architect is reviewing the information provided by a customer for a new vSphere solution design. The customer has stated that some of the virtual machines (VMs) that will be hosted on the new solution handle credit card information from their users as part of an online payment application, and that some of the information will need to be stored temporarily to allow transactions to be completed. Therefore, the solution must be designed to be able to mask or hash the stored information as they will need to show compliance against common industry standards that contain references to the requirements for handling sensitive information.
Which design quality is being requested by the customer?
An architect is conducting interviews to gather requirements for a new vSphere-based private cloud solution.
The following information has been provided by the customer:
The customer, after 10years within an outsourced managed service contract, has decided to bring application hosting back in-house but lacks the VMware skills to support this.
The customer currently has 5,000 workloads under contract and managed by their partner.
The customer would like to keep IT infrastructure costs at a minimum.
The customer would like to ensure that the solution supports the company's green IT agenda by reducing their carbon footprint.
Which statement is classified as a business factor that would impact the design?