Q1:
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
○
A
majority rule technique.○
B
nominal group technique.○
C
Delphi technique,○
D
idea/mind mapping technique.
GAQM
APM-001
Q2:
Exhibit A is an example of which of the following types of Sequence Activities?

○
A
Activity-on-arrow diagramming○
B
Precedence diagramming○
C
Project schedule network diagramming○
D
Mathematical analysis diagramming
GAQM
APM-001
Q3:
Funding limit reconciliation is a tool and technique used in which process?
○
A
Control Costs○
B
Determine Budget○
C
Estimate Costs○
D
Control Budget
GAQM
APM-001
Q4:
An input of the Create WBS process is:
○
A
requirements documentation.○
B
scope baseline.○
C
project charter.○
D
validated deliverables.
GAQM
APM-001
Q5:
Which of the following are three inputs to the risk register?
○
A
Risk register updates, stakeholder register, and quality management plan○
B
Communication management plan, enterprise environmental factors, and activity duration estimates○
C
Risk management plan, activity cost estimates, and project documents○
D
Project scope statement, organizational process assets, and scope baseline